- Projects
Double Tier Mezzanine Installation
Project Overview
New Heights Installations was appointed to deliver a complete 1,200m² double tier mezzanine floor installation for a customer in the North West.
The project included the full mezzanine structure together with a complete 60 minute fire protection package, providing substantial additional usable floor space across two levels.
Scope of Works
The project included:
* 1,200m² double tier mezzanine floor
* 60 minute fire rated suspended ceilings
* Fire rated fascia protection
* Fire protection to structural columns
* Up and over pallet safety gates
* Staircases and associated access
* All required finishing works
Working Around a Live Operation
The customer remained fully operational throughout the installation. Our team worked closely with them to coordinate each stage of the project, allowing their day to day operations to continue with minimal disruption.
Delivered Four Days Ahead of Programme
Through careful planning and efficient installation, the complete project was delivered four days ahead of programme and within budget.
From the mezzanine structure and pallet gates through to the suspended ceilings and complete fire protection package, New Heights Installations managed the works as a complete solution.
Complete Mezzanine Solutions
New Heights Installations provides mezzanine floor installation, fire protection, suspended ceilings, fascia protection, column casings, pallet gates and associated fit out works throughout the UK.
Whether you require a new mezzanine, an extension or alterations to an existing structure, we can provide a complete installation package.

“New Heights Installations exceeded my expectations with their professional and reliable service. The suspended ceilings they have installed is of a high standard and I would use them again without hesitation. I highly recommend New Heights Installations to anyone in need of their services”
Mark Webb | Hill Helicopters